Keeping Dagenham Heathway Moving: MIFL’s Overnight Ramp Renewal for TfL

At MIFL, we take pride in delivering durable, safety focused solutions that keep the UK’s public infrastructure moving, even in the most time-sensitive environments.

Our recent project at Dagenham Heathway Underground Station, carried out for JNG Construction, is a great example of how precision, teamwork, and technical expertise combine to make that possible.

The station ramp, which connects ground level to the District Line platform, had last been fitted back  in 2007 with a Ref 16 pedestrian-grade surface. After almost 20 years of constant footfall at a station which operates from 5:15am to 11.30pm the panels had reached the end of their service life.

Adding some complexity to the project the site team discovered areas of blown concrete once the original panels were removed. This required a revised repair solution, whilst maintaining public access and working to a very tight overnight schedule.

MIFL supplied and installed 9mm panels with a Reference 216 top finish in charcoal, featuring white directional chevrons and chamfered lead-on and lead-off panels for improved safety and visibility.

To ensure durability and a smooth transition between the ramp and the platform, our team used a full suite of MIF Grip Fast- Curing products, including:

– Primer, Flexible Slurry, and Colourcoat with 16mesh aggregate for a seamless finish.

– Floor Screed and Levelling & Bedding Mortar to repair and reinforce the concrete substrate.

– MIF Grip Panel Fixing Kits and Soudal 40 for clean, secure joints.

The result was a secure ramp surface designed for long term performance and safety under heavy pedestrian use.

With operations restricted to overnight windows between 10:00pm and 5:00am, and one side of the ramp required to remain open until 1:00am, meticulous planning was key.

The works were carried out in two phases, one week in July and one week in September to accommodate the additional repair work and ensure full client approval. Despite the constraints, the project was delivered on schedule and with minimal disruption to passengers.

“Our Managing Director has asked me to pass on his gratitude for the quality installation so far. We’ve been particularly impressed with your team’s excellent PPE discipline, professional standards, and clear communication. Site discipline and installation standards have been outstanding — please extend our thanks to everyone involved.” – JNG Construction Site Supervisor

Replacing the 2007 panels with a superior Ref 216 finish gives Dagenham Heathway Station a ramp built for the next two decades of service. The project highlights how MIFL solutions enhance both safety and longevity in high-traffic public environments.

This project showcases MIFL’s ability to adapt, plan, and deliver under pressure, working closely with our client to achieve results.

MIFL, delivering flooring and infrastructure solutions built on safety, quality, and collaboration.

Looking for a partner you can trust with your next infrastructure project?

Call us on 01252 781314 or email info@mifl.co.uk to start the conversation.