Improving Safety at Rugby Rail Depot

Recently, our team completed a cross hatching installation at Rugby Rail Depot for Colas Rail, helping to deter unsafe pedestrian behaviour under active roller shutter doors while working around tight operational constraints.
This project required careful planning, specialist materials, and precise execution to deliver a durable, high visibility solution in challenging conditions.
The solution we proposed..
1) To mechanically abrade the surface of the existing concrete with vacuum-captive, dust free shot
blasting to remove surface contaminants and laitance and provide acceptable key for overlayment.
2) The four doorways leading out from the stores and the welding shop, that have defective steel runners, will have additional preparation by removing steel tracks and the defective and broken concrete either side of the steel tracks, priming with MIF Grip FC Damp Primer and screeding with MIF Grip FC Floor Screed flush with surround.
3) To then mask up the rectangle and apply one coat of MIF Grip FC Damp Primer to the prepared concrete at a rate of 2.5m2/kg and whilst still wet to blind with 1-1.6mm Bassalt.
4) Mask up each of the doorways according to the matrix, and to roller apply one coat of MIF Grip FC Colourcoat in RAL1023 over the entire rectangle at a rate of 2.5m2/kg leaving a uniform-coloured surface.
5) Masking to then set up the 300mm yellow, plus 300mm black chevron pattern and apply one coat of MIF Grip FC Colourcoat in black into the black chevrons.
We managed to complete this in just two days working around heavy rain and howling gales.